In light of
the growing need to improve quality in construction projects, it is vital to
limit and eliminate reworks, which can be accomplished by understanding their
origins and identifying their causes. So, in terms of causes and categories,
this study investigates reworking local projects. Data was gathered through a
questionnaire that identified several variables that contributed to the
reworking. Human, coordination and communication, technical and engineering,
owner, project management, contract, and design was the seven major headings
for these variables. To group the variables into core factors, the responses
were further condensed using factor analysis. According to the findings of this
study, the causes of reworks were inexperienced staff, project execution after
a long period of study, a short term provided by the owner, poor whole project
management, and insufficient study or project before bidding, as well as
separation of design and execution Finally, this study concluded that a
thorough commitment to quality management policy implementation will result in
fewer reworks on building projects.
Country : Egypt
IRJIET, Volume 6, Issue 8, August 2022 pp. 42-52