Effect of Pile Foundation Implementation on Environment, Cost of Elevated Railway Line Construction Project Between Solo Balapan-Kadipiro KM 104+700 to KM 107+000 (Phase II)

Abstract

With the development of traffic flow, infrastructure development is needed to create comfort and safety in driving. In addition, the development must also be supported by good traffic management in order to reduce the traffic density of vehicles, one of which is the construction project of the Elevated Railway Line between Solo Balapan - Kadipiro KM.104+700 to KM.107+000 (Phase II). This research was taken from the Elevated Railway Development Project between Solo Balapan-Kadipiro KM+ 104+700 to 107+000 (Phase II), which is located at the Joglo Intersection in Banjarsari Village, Surakarta City. The research method used is quantitative and qualitative research methods. From the research results of pile driving work: air pollution, noise pollution, and vibration caused by the pressure of the drop hammer tool hitting the pile, from these influences, the main effect is that the vibration caused results in buildings and building structures, so that many influences interfere with human comfort. The amount of analysis of the bearing capacity of the pile: (1) The stress that occurs in the transportation of 32.67

Country : Indonesia

1 Aisyah Fidina Bella2 Co. Prof. Muhammad Nur Sahid

  1. Civil Engineering, Universitas Muhammadiyah Surakarta, Indonesia
  2. Civil Engineering, Universitas Muhammadiyah Surakarta, Indonesia

IRJIET, Volume 7, Issue 3, March 2023 pp. 132-141

doi.org/10.47001/IRJIET/2023.703020

References

  1. A.S. Anto Budi Listyawan, Renaningsih,Qunik Wiqoyah, Mekanika Tanah dan Rekayasa Pondasi. Jl.A.Yani Tromol Pos 1 Kartasura,Surakarta 57102, 2017.
  2. Joseph E.Bowles, Analisa dan desain Pondasi. 1982.
  3. Pemerintah Pusat, Peraturan Pemerintah Republik Indonesia No 50 Tahun 2012 Tentang Penerapan Sistem Manajemen Keselamatan dan Kesehatan Kerja, no. Cd. Indonesia: LN. 2012 No. 100, TLN No. 5309, LL SETNEG : 17 HLM, 2012, p. b. usaha-usaha. [Online]. Available: https://peraturan.bpk.go.id/Home/Details/5263/pp-no-50-tahun-2012
  4. M. Nur Sahid, I. Setiyaningsih, M. Solikin, and J. J. Christianto, “Kajian Faktor-Faktor Penyebab Cost Overrun Oleh Kontraktor Pada Proyek Jalan Apbd Kabupaten Sukoharjo Tahun 2017 Dan 2018,” J. Tek. Sipil, vol. 8, no. 2, pp. 79–88, 2019, doi: 10.24815/jts.v8i2.14231.
  5. M. N. Sahid, A. B. Listyawan, A. Rochman, and R. D. H. Rim, “Analisis Faktor Dominan yang Mengakibatkan Pembengkakan Biaya oleh Kontraktor pada Proyek Jalan Kabupaten Wonogiri APBD Tahun 2017 dan 2018,” Cantilever, vol. 8, no. 2, pp. 51–57, 2020, doi: 10.35139/cantilever.v8i2.8.
  6. Hary Chrystady Hardiyatmo, Analisis dan Perencanaan Pondasi I dan II. Yogyakarta: Gadjah Mada University Press, 2015.
  7. Ir Sardjono HS, Pondasi Tiang Pancang Jilid 1. 1998.
  8. PT Mitra Adi Pranata, “LAPORAN BULAN 11 BULAN oktober 2022,” Jl. Cemara Raya No. 45, Banyumanik, Semarang, Jawa Tengah 50267, 2022.
  9. P. M. A. Pranata, “LAPORAN BULAN 12,” Jl. Cemara Raya No. 45, Banyumanik, Semarang, Jawa Tengah 50267, 2022.
  10. M. N. Sahid and N. Widiana, “Investigasi Faktor Penyebab Cost Overrun Oleh Kontraktor Pada Proyek Jalan Apbd Kabupaten Karanganyar Tahun 2017 Dan 2018,” Wahana Tek. Sipil J. Pengemb. Tek. Sipil, vol. 26, no. 1, p. 25, 2021, doi: 10.32497/wahanats.v26i1.2645
  11. “View of IDENTIFIKASI FAKTOR DOMINAN RISIKO COST OVERRUN PADA PROYEK JALAN KABUPATEN BOYOLALI TAHUN 2017 DAN 2018.pdf,” vol. IV, pp. 59–64, 2019, doi: https://doi.org/10.32511/juteks.v4i2.338
  12. T. A. Muhammad Nur Sahid, “Pengendalian Kinerja dan Produktivitas Pembangunan Gedung Bertingkat 4 Lantau Untuk Parkir Roda Dua Di Universitas Muhammadiyah Surakarta,” Din. Tek. Sipil, vol. 11, pp. 45–53, 2011.
  13. R. Ariana, “Penyelidikan Tanah Pada Underpass Simpang joglo Pekerjaan Manajemen Konstruksi Pembangunan Jalur Ganda Solo - Semarang Fase 1 (Solo Jebres - Solo Balapan - Kadipiro - Kalioso) Donohudan -,” Bandung, 2021.